About the Project

We’re excited that Expedia Group will be arriving in Seattle in the fall of 2019 as we settle in at our new campus in the Interbay neighborhood along the Elliott Bay waterfront. Our new campus is the physical embodiment of our identity and vision to be the world’s travel platform. It’s an unmatched employee experience – a destination where people with a passion for tech and travel do their best work. We can’t wait to become neighbors in a community we care deeply about.


CONSTRUCTION UPDATES

WHAT’S HAPPENING IN NOVEMBER 2019 


GLY continues overall site improvements with restoration of interior spaces 
and exterior cladding. This work includes: 

  • Portions of the office buildings are now occupied by Expedia Group employees. 

  • 30 public parking stalls are available in the Northwest parking garage, located on Galer Street.  

  • Exterior painting of existing buildings. 

  • General: delivery of equipment and materials to the site, increased work force and trucks,

  • noise created by construction, and equipment operation. 

  • Continue installation of temporary storm water erosion control measures

  • (grading and installing silt fencing, retention ponds, and storm water collection piping). 

  • Continuation of grading and earthwork in preparation for site work. 

  • Installation of landscaping trees and ground cover throughout site.  

  • Exterior window system being installed on NW expansion building

 

WORK HOURS

Non-holiday weekdays (Monday-Friday): 7:00 a.m. to 6:00 p.m.

 

FOR YOUR SAFETY

  • The construction fencing surrounding the project is for safety and security;

  • Please do not enter the project site at any time for any reason.

  • Be mindful of equipment and truck traffic in the surrounding areas until project is complete.

  • Be alert to truck back-up alarms and wide turns, and do not cross between trucks and trailers.

  • Always follow instructions of the flaggers in the construction areas.

 

CONSTRUCT ION HOTLINE

Community members seeking additional information and support or on-site safety

or emergency concerns, should contact our 24/7 construction hotline at (425) 451-

8877.

 

WHAT’S HAPPENING IN OCTOBER 2019

GLY continues overall site improvements with restoration of interior spaces

and exterior cladding. This work includes:

  • Exterior painting of existing buildings.

  • General: delivery of equipment and materials to the site, increased work

  • force and trucks, noise created by construction, and equipment operation.

  • Continue installation of temporary storm water erosion control

  • measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of landscaping trees and ground cover throughout site.

  • New Bike trail is currently open. Detour along Alaskan way will no longer be in use.

  • Continuation of elevated deck assembly supporting the NW offices.

  • Portions of Expedia office space have received occupancy.

  • 30 public parking stalls are available in the Northwest parking garage, located on Galer Street.

 

WHAT’S HAPPENING IN SEPTEMBER 2019 


GLY continues overall site improvements with restoration of interior spaces 
and exterior cladding. This work includes: 
 

  • Exterior painting of existing buildings. 

  • General: delivery of equipment and materials to the site, increased work  force and trucks,

  • noise created by construction, and equipment operation. 

  • Continue installation of temporary storm water erosion control measures

  • (grading and installing silt fencing, retention ponds, and storm water collection piping). 

  • Continuation of grading and earthwork in preparation for site work. 

  • Installation of landscaping trees and ground cover throughout site.  

  •  New Bike trail will be opening along water front early September. Current detour along

  • Alaskan way will no longer be in use immediately following.  

  • Continuation of elevated deck assembly supporting the NW offices. 

  • Street restoration work on Galer and Alaska Way will be completed in September.  

 
WORK HOURS 


Non-holiday weekdays (Monday-Friday): 7:00 a.m. to 6:00 p.m. 
 
FOR YOUR SAFETY

 

  • The construction fencing surrounding the project is for safety and security; please do not enter the

  • project site at any time for any reason. 

  • Be mindful of equipment and truck traffic in the surrounding areas until project is complete. 

  • Be alert to truck back-up alarms and wide turns, and do not cross between trucks and trailers. 

  • Always follow instructions of the flaggers in the construction areas. 

 
CONSTRUCTION HOTLINE 
Community members seeking additional information and support or on-site safety 
or emergency concerns, should contact our 24/7 construction hotline at (425) 451- 
8877. 

 

August 

GLY continues overall site improvements with restoration of interior spaces
and exterior cladding. This work includes:

  • Exterior painting of existing buildings.

  • General: delivery of equipment and materials to the site, increased work force and trucks, noise created by construction, and equipment operation.

  • Continue installation of temporary storm water erosion control measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of landscaping trees and ground cover throughout site.

  • The bike trail from Centennial Park (fishing pier) to Galer St. is being rebuilt and upgraded with new separate bike and pedestrian paths. See reverse for details on the detour.

  • Continuation of elevated deck assembly supporting the NW offices.

  • Continued street restoration work on Galer and Alaska Way.

WORK HOURS


Non-holiday weekdays (Monday-Friday): 7:00 a.m. to 6:00 p.m.

FOR YOUR SAFETY

  • The construction fencing surrounding the project is for safety and security; please do not enter the project site at any time for any reason.

  • Be mindful of equipment and truck traffic in the surrounding areas until project is complete.

  • Be alert to truck back-up alarms and wide turns, and do not cross between trucks and trailers.

  • Always follow instructions of the flaggers in the construction areas.

  • Public access to 16th Avenue W. and to the Elliot Bay Trail from W. Galer to the pier will be closed through the fall of 2019. Bike and pedestrian traffic will continue to be rerouted to Alaskan Way, which is temporarily single lane for motorized vehicles. Obey flaggers during construction hours and automated traffic signaling outside construction hours.

 

July 


GLY continues overall site improvements with restoration of interior spaces
and exterior cladding. This work includes:

  • Exterior painting of existing buildings.

  • General: delivery of equipment and materials to the site, increased work

  • force and trucks, noise created by construction, and equipment operation.

  • Continue installation of temporary storm water erosion control measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of landscaping trees and ground cover throughout site.

  • The bike trail from Centennial Park (fishing pier) to Galer St. is being rebuilt and upgraded with new separate bike and pedestrian paths. 

  • Continuation of elevated deck assembly supporting the NW offices.

WORK HOURS

Non-holiday weekdays (Monday-Friday): 7:00 a.m. to 6:00 p.m.

FOR YOUR SAFETY

 

  • The construction fencing surrounding the project is for safety and security; please do not enter the project site at any time for any reason.

  • Be mindful of equipment and truck traffic in the surrounding areas until project is complete.

  • Be alert to truck back-up alarms and wide turns, and do not cross between trucks and trailers.

  • Always follow instructions of the flaggers in the construction areas.

  • Public access to 16th Avenue W. and to the Elliot Bay Trail from W. Galer to the pier will be closed through the fall of 2019. Bike and pedestrian traffic will continue to be rerouted to Alaskan Way, which is temporarily single lane for motorized vehicles. Obey flaggers during construction hours and automated traffic signaling outside construction hours.

MAY

 

GLY continues overall site improvements with restoration of interior spaces
and exterior cladding. This work includes:

 

  • Exterior painting of existing buildings.

  • General: delivery of equipment and materials to the site, increased work

  • force and trucks, noise created by construction, and equipment operation.

  • Continue installation of temporary storm water erosion control measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of piped and electrical underground utilities on site.

  • The bike trail from Centennial Park (fishing pier) to Galer St. is being rebuilt and upgraded with new separate bike and pedestrian paths. 

  • Continuation of slab on grade placement supporting NW office and start of elevated deck assembly.

APRIL


GLY continues overall site improvements with restoration of interior spaces and exterior cladding. This work includes:

  • General: delivery of equipment and materials to the site, increased work force and trucks, noise created by construction, and equipment operation.

  • Continue installation of temporary storm water erosion control measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of piped and electrical underground utilities on site.

  • The bike trail from Centennial Park (fishing pier) to Galer St. is being rebuilt and upgraded with new separate bike and pedestrian paths. 

  • Start of slab on grade placement supporting NW office structure.

MARCH


GLY continues overall site improvements with restoration of interior spaces and exterior cladding. This work includes:

 

  • General: delivery of equipment and materials to the site, increased work force and trucks, noise created by construction, and equipment operation.

  • Continue installation of temporary storm water erosion control measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of piped and electrical underground utilities on site.

  • The bike trail from Centennial Park (fishing pier) to Galer St. is being rebuilt and upgraded with new separate bike and pedestrian paths. 

  • Foundation and slab on grade work continues for existing building expansion.

  • Start of slab on grade placement supporting NW office structure.

  • Tower crane removal supporting new parking structure.

  • Tower crane installation supporting NW office structure.

FEBRUARY


GLY continues overall site improvements with restoration of interior spaces and exterior cladding. This work includes:

 

  • Continue installation of temporary storm water erosion control measures (grading and installing silt fencing, retention ponds, and storm water collection piping).

  • Continuation of grading and earthwork in preparation for site work.

  • Installation of piped and electrical underground utilities on site.

  • General: delivery of equipment and materials to the site, increased work force and trucks, noise created by construction, and equipment operation.

  • The bike trail from Centennial Park (fishing pier) to Galer St. is being rebuilt and upgraded with new separate bike and pedestrian paths. 

  • Foundation and slab on grade work continues for existing building expansion.

  • Final elevated slab pour for the new parking structure.

  • Foundation pile work for new NW office structure continues.

  • Below grade mechanical will be installed within the new NW Office structure.


CONSTRUCTION HOTLINE

Community members seeking additional information and support or on-site safety
or emergency concerns, should contact our 24/7 construction hotline at (425) 451-
8877.